M. Cappucci, Manager of Engineering, provided a summary of the events that have occurred with respect to this project, explaining that the purpose of this project is to clean out the drain and stabilize the banks. A Public Information Centre was held recently giving land owners an opportunity to ask questions about the project.
G. Rood, Drainage Engineer, reviewed his report for Council, and explained the works incorporated in the project.
Mr. Rood advised that his office has not received any inquiries.
Mr. Rood advised that he was contacted by the Essex Region Conservation Authority regarding a discrepancy in the pipe sizes shown in the report. He confirmed that an addendum of the report was provided to ERCA and Town staff and recommended that the amendment page be sent out to residents along with the notice of Court of Revision for St. Michael's Drain.
No public questions were received.